Numbers out of step.
Inventory, open orders and demand are counted in different systems at different times.
Introducing Resolve, our fast decision-making model. Meet Resolve →
See the shortage before the line stops. Every part. Every order. Every lead time.
See it worked throughStock, demand and supply live in different systems, updated on different days. By the time a shortage shows up in one report, the line is already waiting for the part.
Inventory, open orders and demand are counted in different systems at different times.
Plans use the lead time the supplier quotes, not the one they actually deliver.
The shortage is noticed when a job can’t start.
Stock on hand, what’s on order, what’s due to be used and how suppliers actually perform, read together every day.
One shortage watch. Every projection shows its inputs.
A shortage watch planners can act on: when each part runs out, why, and what can still be done about it.
9 covered · 2 tight · 1 short
| Part | Description | Status | Projection | Buyer |
|---|---|---|---|---|
| Rotating spares | ||||
| BRG-6205 | Bearing, deep groove | Short | Runs out in 9 days; next delivery in 14 | MRO buyer |
| SEAL-114 | Mechanical seal kit | Tight | Below safety stock in 20 days | MRO buyer |
| MTR-7K | Motor, 7.5 kW | Covered | Covered to day 45 | MRO buyer |
| Consumables | ||||
| GSK-88 | Gasket set | Tight | Supplier late on the last 3 orders | MRO buyer |
| FLT-30 | Filter cartridge | Covered | Covered to day 38 | Stores |
| LUB-46 | Lubricant, 20 L | Covered | Covered to day 60 | Stores |
| FST-M12 | Fasteners, M12 | Covered | Covered to day 90 | Stores |
| Production parts | ||||
| VLV-2B | Valve body | Covered | Covered to day 33 | Production buyer |
| HSG-40 | Housing | Covered | Covered to day 41 | Production buyer |
| PCB-7 | Controller board | Covered | Covered to day 52 | Production buyer |
| SNS-12 | Pressure sensor | Covered | Covered to day 36 | Production buyer |
| CBL-3 | Cable harness | Covered | Covered to day 44 | Production buyer |
Stock
14 on hand. Three lines use 1.6 a day between them.
WMS · bin B-12-04On order
20 due in 5 days, confirmed by the supplier.
PO-77120 · confirmation emailHistory
This supplier has delivered this part 9 days late on average this year.
Goods receipts · 11 ordersProjection
Stock runs out on day 9. The delayed order arrives around day 14.
Shortage model · daily run1Short
2Tight
9Covered
To act on
Sign-off
The AI finds the gap and the options. Buyers decide.
Illustrative example. Parts, suppliers and quantities are fictional.
Your ERP stays the record. The AI reads it, and everything around it.
Supplier emails, PDFs and portals, not just the fields in the purchase order.
How Sense works ↗Projections use how suppliers actually deliver, not what they quote.
How Anticipate works ↗Expedites and transfers are raised as requests in your own systems.
APIs & connectors ↗The data behind a shortage answers other questions too.
Does this PO match what we’re paying?
Find mismatches before payment.
See how →What needs maintenance, and when?
Decide what should be maintained, and when.
See how →What fails next?
Spot the patterns and warn what may fail next.
See how →Which invoices are we overpaying?
Catch overbilling, duplicates and mistakes before payment.
See how →Send the orders and stock history around it. We’ll show you when the AI would have raised it.
Talk to us →